Building a new Northgate Branch

Capital Project Information

New Central Library

Neighborhood Branches

LFA News Releases

Information for Architects, Consultants, Contractors & Bidders

Oversight & Citizen Review

Financial Summaries

Archive

 

Libraries for All
Capital Program Office:
capital.program@spl.org
1000 Fourth Ave.
Seattle, WA 98104
206-386-4624

 


Photo Gallery

Watch the Northgate project take shape in a series of photographs devoted to the building process. The project includes the 10,000-square-foot Northgate Branch, and Seattle Parks and Recreation's 20,000-square-foot community center and 1.67-acre park. The most recent activity is shown at the top of the page.

Click on image to see larger version.


June 2006

The children's area inside the library takes shape. Landscaping, benches and the children's play area at the community center are installed outside.

Construction Photo - Jun. 2006 Construction Photo - Jun. 2006 Construction Photo - Jun. 2006 Construction Photo - Jun. 2006

May 2006

Final details are installed on the library, including the art glass near the book drops.

Construction Photo - May 2006 Construction Photo - May 2006 Construction Photo - May 2006 Construction Photo - May 2006

April 2006

The framework for the shelving in the library is installed. The lawn in the new park and the streetwork begin to take shape.

Construction Photo - Apr. 2006 Construction Photo - Apr. 2006 Construction Photo - Apr. 2006 Construction Photo - Apr. 2006

March 2006

Painting concludes on the exterior of the library while the raised floor is installed over the mechanical systems on the interior.

Construction Photo - Mar. 2006 Construction Photo - Mar. 2006 Construction Photo - Mar. 2006 Construction Photo - Mar. 2006

February 2006

Interior work progresses at the library as windows and drywall are installed.

Construction Photo - Feb. 2006Construction Photo - Feb. 2006 Construction Photo - Feb. 2006Construction Photo - Feb. 2006

January 2006

The contractor completes construction of the library roof, allowing interior work to begin.

Construction Photo - Jan. 2006Construction Photo - Jan. 2006 Construction Photo - Jan. 2006Construction Photo - Jan. 2006

December 2005

The brickwork is under way at the library as the grass in the park area begins to grow.

Construction Photo - Dec 2005Construction Photo - Dec. 2005 Construction Photo - Dec. 2005Construction Photo - Dec 2005

November 2005

The exterior walls are framed at the library as brickwork begins on the community center.

Construction Photo - Nov 2005Construction Photo - Nov 2005 Construction Photo - Nov 2005Construction Photo - Nov 2005

Ocbober 2005

The steel structure for the library begins to take shape. The park was hydro-seeded so the seed could sprout before winter.

Construction Photo - Oct 2005Construction Photo - Oct 2005 Construction Photo - Oct 2005Construction Photo - Oct 2005

September 2005

Site development begins as the steel structure for the community center is put in place.

Construction Photo - Sept 2005Construction Photo - Sept 2005 Construction Photo - Sept 2005Construction Photo - Sept 2005

August 2005

Concrete slabs are poured to form the floor of the library as the concrete block gymnasium is completed at the community center.

Construction Photo - Aug 2005Construction Photo - Aug 2005 Construction Photo - Aug 2005Construction Photo - Aug 2005

July 2005

Formwork foundations and concrete slabs begin to take shape at the new library and community center.

Construction Photo - July 2005Construction Photo - July 2005 Construction Photo - July 2005Construction Photo - July 2005

June 2005

Formwork and reinforcements are placed for the future walls of the community center.

Construction Photo - June 2005Construction Photo - June 2005 Construction Photo - June 2005Construction Photo - June 2005

May 2005

The storm water vault begins to take shape and foundation work continues on the community center.

Construction Photo - May 2005Construction Photo - May 2005 Construction Photo - May 2005Construction Photo - May 2005

April 2005

The existing storm drain on the site is removed and excavation begins for both the storm water vault and the community center.

Construction Photo - April 2005Construction Photo - April 2005 Construction Photo - April 2005Construction Photo - April 2005

March 2005

The existing buildings on the site are demolished.

Construction Photo - March 2005Construction Photo - March 2005 Construction Photo - March 2005Construction Photo - March 2005

 

 


 