Watch the new 5,652-square-foot Montlake Branch take shape in a series
of photographs devoted to the building process. The most recent activity
is shown at the top of the page.
March 2006
Installation of
masonry and wood
siding begins as
work on interior
finishes continues.



February 2006
Installation of
heating and ventilation
systems begins as
windows are put in
place.



January 2006
Installation of
steel columns begins
as construction of
exterior walls continues.
The meeting room
begins to take shape.



December 2005
Construction of
the exterior walls
continues. The ceiling
begins to take shape.



November 2005
Construction of
the staff area wall
foundation begins.
Following the completion
of the foundation,
the concrete floor
slab is poured and
completed.



October 2005
Construction of formwork for the parking garage wall begins.



September 2005
Grading of the site and excavation for footing construction begin.
Construction of footing for the foundation walls begins.



August 2005
Existing houses and pavement are demolished during the first week
of construction to make way for the new building.