Logo   Libraries for All,  Capital Projects

Libraries for All Index            Library Home Page

Return to Lake City
Branch Home Page

Building an Expanded Lake City Branch and Neighborhood Service Center

Capital Project Information

New Central Library

Neighborhood Branches

LFA News Releases

Information for Architects, Consultants, Contractors & Bidders

Oversight & Citizen Review

Financial Summaries

Archive

 

Libraries for All
Capital Program Office:
capital.program@spl.org
1000 Fourth Ave.
Seattle, WA 98104
206-386-4624

 


Photo Gallery

Watch the expanded 15,300-square-foot Lake City Branch and a 5,000-square-foot neighborhood service center take shape in a series of photographs devoted to the building process. The most recent activity is shown at the top of the page.

Click on image to see larger version.


August 2005

The branch, plaza and park near completion.

Construction Photo - May/June 2005Construction Photo - May/June 2005

Construction Photo - May/June 2005Construction Photo - May/June 2005

July 2005

Work continues on the interior of the branch. Benches and lighting are installed outside.

Construction Photo - May/June 2005Construction Photo - May/June 2005

Construction Photo - May/June 2005Construction Photo - May/June 2005

June 2005

The interior spaces begin to take shape as walls are built.

Construction Photo - May/June 2005Construction Photo - May/June 2005

Construction Photo - May/June 2005Construction Photo - May/June 2005

May/June 2005

The children's area begins to take shape as interior walls are constructed. Installation of the elevator nears completion.

Construction Photo - May/June 2005Construction Photo - May/June 2005

March/April 2005

Art for the Albert Davis Park, which is on the same site as the branch, is installed. The artwork, created by artist Perri Lynch, consists of eight pre-cast concrete wave form sculptures that mark the presence of water in the landscape and symbolically embody both the tranquil and dynamic states of water. With structural steel erection completed, the contractor begins building the exterior walls.

Construction Photo - March/April 2005Construction Photo - March/April 2005

January/February 2005

The building begins to take shape as structural steel is erected.

Construction Photo - January/February 2005Construction Photo - January/February 2005

November/December 2004

Contractors complete construction of the rectangular concrete planter (left photo, center) along 28th Ave. N.E. The entrance to the new parking garage takes shape.

Construction Photo - November/December 2004Construction Photo - November/December 2004

September/October 2004

Contractors place the underground duct-work for the branch. The layout of the garage takes shape as the columns are completed.

Construction Photo - September 2004Construction Photo - September 2004

 
August 2004

Concrete forms are removed from the garage as the walls take shape. A crane sets into place reinforcing steel for the garage columns.

Construction Photo - August 2004Construction Photo - August 2004

June/July 2004

Excavation continues on the underground parking garage and the garage detention system.

Construction Photo - June/July 2004Construction Photo - June/July 2004

April/May 2004

Select demolition and excavation of underground duct-work at the branch begins.

Construction Photo - April May 2004Construction Photo - April/May 2004

 

 


Content modified: 28 August 2005

 

12/30/2005

© 1999-2006 - The Seattle Public Library