Watch the expanded 16,493-square-foot Douglass-Truth Branch take shape
in a series of photographs devoted to the building process. The most
recent activity is shown at
the top of the page.
February 2006
Interior framing of the addition continues.


January 2006
Roof joists are built on site and installed. The upper section
of the monumental stair is prepared for placement.


December 2005
Installation of the steel framework begins. The monumental stair
is built at the steel fabricator's shop and prepared for delivery.


November 2005
The contractor begins building the enclosure for the air conditioning
system. The floor of the meeting room takes shape.


October 2005
Construction of the eastern foundation wall is complete. Piping
is installed in the expansion.


September 2005
Construction of concrete formwork nears completion under the existing
building.


August 2005
The contractor builds formwork for the foundation walls. New data
telecommunications lines are installed inside the existing building.


July 2005
Excavation for the addition to the branch begins. Shoring is completed
in late July.


June 2005
Select demolition of the interior of the existing branch begins.