Watch the expansion of the Broadview Branch take shape in a series of photographs devoted to the building process. The most recent activity is shown at the top of the page.
Click on image to see larger
version.
August/September 2007
The parking lot is prepared for paving. Street improvements along Greenwood Avenue North begin. Concrete is poured for the west entrance to the branch.
 
 
June/July 2007
Installation of exterior finishes is complete. Installation of the new sidewalk outside the branch begins. Installation of miscellaneous interior trims and fixtures begins.
 
 
April/May 2007
Preparation begins for application of the exterior siding as the roofing installation nears completion. Gypsum wallboard inside the branch is prepared for painting. Interior installation of data cable trays and the acoustical ceiling system begins.
 
 
February/March 2007
The addition takes shape as work continues on framing the walls and the roof.
 
 
November/December 2006
The concrete floor slab of the expansion is completed and work is under way on the interior walls and the roof.
 
 
August/September 2006
Partial demolition of the existing library building is completed and formwork begins for the addition.
 
 