|
Building a New Central Library |
|
|
Return
to Building a New
Central Library
|
Central Library Status Report
Project description
- Replace the 206,000-square-foot
library, which opened in 1960, on the existing
location at 1000 Fourth Ave.
- The new library has: an
expanded collection capacity of 1.4 million
books and materials; 11 floors; underground
parking; spacious areas for children and young
adults; a four-level "books spiral"
to house the bulk of the non-fiction collection
in a continuous run; an auditorium; a floor
called the "mixing chamber" that
contains information desks where patrons can
ask librarians for help; multilingual and
English-as-a-second-language areas; a coffee
cart; and an exterior "skin" of
insulated glass on a steel structure.
- A 130,000-square-foot temporary facility at 800 Pike
St. in the expanded Washington State Convention and Trade Center opened
July 7, 2001, and closed April 30, 2004.
Key contacts for the new
Central Library
- Capital program office: (206) 615-1698, e-mail: capital.program@spl.org
- Director of Public Services: Jill Jean, (206) 386-4678
- Central Library, 1000 Fourth Ave., Seattle, WA 98104
|
|
Milestones
- July 2004: The Seattle Public Library
board of trustees selected a third artist
to create permanent artwork as part of the
“Library Unbound” project.
- May 2004: The Central Library opened
at 11 a.m. Sunday, May 23. Nearly 26,000 visited
the building on its first day of operation.
- January 2004: Glass exterior installation
completed. Overall construction 91 percent
completed. The Library Board selected two
artists to create permanent artwork as part
of the “Library Unbound” project.
- November 2003: The Central Library
received its first award – a Steel Design
Award of Excellence from the British Columbia
Region of the Canadian Institute of Steel
Construction for innovative use of steel.
- June 2003: The Library Board selected
four artists to present proposals for permanent
artworks as part of the “Library Unbound”
project.
- May 2003: On May 7, workers raised
the last piece of structural steel (a four-ton
piece of seismic grid steel) topped by the
traditional tree and American flag. Construction
50 percent completed.
- December 2002: Steel
erection began. The steel structure will support
the insulated glass and metal mesh exterior
“skin.” Subcontractor bidding
substantially completed.
- October 2002: Concrete
structure completed. Permitting completed.
- July 2002: Construction
13 percent completed.
- April 2002: Excavation
and shoring work completed.
- March 2002: Construction
documents completed.
- October 2001: Construction
crews finished salvaging and recycling interior
materials.
- September 2001: Contractors
finished removing asbestos and other hazardous
materials.
- August 2001: Contractors
completed the final landscape
removal plan, the first visible sign of
the start of demolition.
- June 8, 2001: The
existing Central Library at 1000 Fourth Ave.
closed for good to make way for construction
of a bold and exciting new facility. The
Library began moving its books and materials
to a temporary location at 800 Pike St.
- May 2001: Hundreds
of people attended an open house to see images
of the final design of the new library and
learn more about how the innovative building
will look and function.
- March 2001: The Library
and its architects finished the design of
the new Central Library.
- February 2001: William
B. Meyer Inc. was hired to move the books,
furniture and equipment from the Central Library
to temporary quarters at 800 Pike St.
- Throughout 2000:
Members of 37 Library staff work groups gave
architects feedback on the library design.
- December 2000: The Library Board
selected four artists to propose artwork to
be integrated into the new library.
- September 2000: Library
users tested mock-ups of two "books spiral"
floor designs to house the library's non-fiction
collection in a continuous run. The Library
Board selected Jessica Cusick and Rick Lowe
to be art planners, following the recommendation
of an advisory committee that evaluated 14
applications.
- May 2000: Dutch architect
Rem Koolhaas of the Office for Metropolitan
Architecture reviewed progress on the library
design for 1,500 people at a public presentation
at Benaroya Hall. The Library Board selected
Hoffman Construction Co. to be general contractor/construction
manager. Four firms applied for the job.
- January 2000: Members
of the public joined 10 work groups - including
services for children, older adults, young
adults and people with disabilities - to share
their hopes and dreams for the new library.
- December 1999: More
than 1,000 people attended public events at
which architect Rem Koolhaas described his
early vision for the library.
- May 1999: The Library
Board selected architect Rem Koolhaas and
Seattle-based LMN Architects to jointly design
the new library after 1,700 people attended
presentations put on by three finalists. An
advisory panel reviewed the qualifications
of the 29 firms that applied for the job.
The Library selected The Seneca Group to be
project manager. Ten firms applied for the
job.
- November 1998: Seattle
voters passed the $196.4 million "Libraries
for All" bond measure, which included
money to build a new central library on the
existing site at 1000 Fourth Ave.
|
Quick facts
|
Project type
|
Replace existing library
|
|
Schedule for completion
|
2004
|
|
Budget for capital costs
|
$169.2 million (includes $10 million for the Temporary
Central Library)
|
|
Total library program area
|
362,987 square feet
(formerly 206,000 square feet)
|
|
Computers
|
400
(formerly 75)
|
|
Art planners
|
Jessica Cusick and Rick Lowe
|
|
Art budget
|
$899,101
|
|
Central Library Building Committee Library Board
members
|
Gilbert W. Anderson
Linda Larson
|
|
Architects
|
Office for Metropolitan Architecture
LMN Architects
|
|
Contractor
|
Hoffman Construction Co.
|
|
|
Next steps
See also "Libraries
for All" 1998 Capital Plan (issued March 13, 1998).
Content Modified: 22 June 2006
06/22/2006
© 1999-2006
- The Seattle Public Library
|